ISD completes single envelope ‘clad rack’ cold storage facility

ISD Solutions has completed a €1.8m (£1.3m) frozen and chilled storage facility for leading Spanish pharmaceutical and healthcare giant Grifols.

The 12 month project has involved the design and construction of two temperature controlled clad-rack structures to provide centralised storage and distribution for blood plasma products.

The supporting structure comprises a Jungheinrich high-rack storage system, with cranes and conveyors, which provides automated storage, sorting and retrieval, enveloped by high performance insulated panels to form a thermally efficient single envelope skin for each of the two buildings.

In total 9,000m2 of PIR insulated panels were used in the construction.

ISD Solutions had total responsibility for the insulated envelope and door design, creating both a high bay frozen chamber supporting temperatures down to -35 degrees C and an adjacent 35m high chilled storage area.

Achieving an efficient air tight structure was crucial and the buildings easily exceed design specifications with test measurements of 0.4m3 / m2 at 50 Pascals for both chambers.

With the largest panels measuring 18m high, the logistics of lifting and fixing these into position required careful planning for ISD’s Special Projects Division.

With over 500 construction workers involved in total on the whole logistics centre, sequencing and co-ordination with other trades was also critical in achieving the client’s timeframes.

Conveyor and door synchronisation is crucial to the success of the facility operation and were important design considerations that ISD and Jungheinrich had to get right.

ISD Solutions pioneered the design and construction of large scale single envelope cold store projects using self-finished composite panel technology and was chosen as the only contractor with specific experience in building similar clad rack structures.

Early design input with Jungheinrich and main contractor Stewarts Construction also ensured a problem free build.

Ray Barry at Jungheinrich says:“This prestigious contract required specialist sub-contractors that we selected from all over Europe.

ISD Solutions was chosen as our European partner for this project because they have an outstanding track record, unique expertise in design and installation of similar facilities and the best record for air leakage (measured by BSRIA at below 0.1m3 per hour at an increased pressure of 60 pascals).”

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions.

Links may be included in your comments but HTML is not permitted.